Stillwater News

First new transformer arrives at Boomer Lake substation this week

Released:May 15, 2019

MEDIA RELEASE

Boomer Lake substation transformer installed

Credit: City of Stillwater

(STILLWATER, OKLAHOMA / May 15, 2019) – Stillwater Electric Utility received one of the two substation transformers replacing older versions at the Boomer Lake substation Tuesday. The second transformer will arrive later this week. This transformer is the first of six substation transformers ordered to replace aging transformers at other distribution substations.

These new, more reliable transformers will offer a significant increase in capacity for Stillwater’s electric system. The new transformers will provide an increase in capacity from 20 MVA (Million Volt Amps) to 28 MVA each. This increase will not only help with reliability, but will accommodate increasing load on the system.

The transformer arrived Monday evening after a multiday trip from the factory in Canonsburg, Pennsylvania. A 775-ton crane placed the 85,000-pound transformer on its foundation Tuesday morning.

Learn more about the Substation Transformer Replacement Project at http://stillwater.org/page/home/government/current-projects/electric-utility-projects/substation-transformer-replacement-project

-30-

Photo: https://flic.kr/s/aHskRiz1or

For media inquiries, contact the Department of Marketing and Civic Engagement at 405.742.8219 or email news@stillwater.org