Monty Karns, City Engineer
The Stillwater Regional Airport is working to replace the current asphalt apron with a full-strength concrete. Phase 1 is the first of an anticipated four phases, which will expand parking and commercial airline operation space near the terminal.
Anticipated Date (Design): March 2019
Anticipated Date (Construction): March 2020
Anticipated Date (Completion): April 2021
This expansion allows for safer commercial operations through expanded parking capacity by providing full-strength pavement capable of supporting larger aircraft.
This project will be funded with 90% FAA AIP Grant funds and 10% with local funds.
Year Funded: FY2020
Funding Source: 90% Federal Grant / 10% City of Stillwater
Project Budget: Estimated at $5,777,777
Expenditure to date: $2,700,426.00
05.05.2019: Out for Bids
07.23.2019: FAA Grant Awarded
02.04.2019: City Council Resolution No CC-2019-1
06.17.2019: City Council Award of Contract to Contech
04.20.2020: City Council Approves Budget Amendment to Reflect Grant Award
Content last reviewed 01-06-2021
![]() |