Apron Reconstruction: Phase 3 - Center

Apron Reconstruction: Phase 3 - Center 


Project Manager

Monty Karns, City Engineer


What We're Doing

The Stillwater Regional Airport is working to replace the current apron with a new one that expands aircraft parking and operations near the terminal. This will be completed in phases.


Anticipated Milestones

  • Anticipated Date (Design): March 2021

  • Anticipated Date (Construction): December 2021

  • Anticipated Date (Completion): December 2022


Benefits of the Project

This expansion allows for safer commercial operations, larger aircraft parking areas. 


Budget & Funding

This project will be funded with 100% FAA AIP Grant funds. 

  • Year Funded: FY2021

  • Funding Source:  100% Federal Grant

  • Project Budget: $5,400,000

  • Expenditure to date: $2,649,700


Project Management

 


Updates

  • 04.10.2021: Out to Bid

  • 05.05.2021: Bid Opening

  • 05.17.2021: Contract Award to Contech 


Actions Authorized by City Council


Center Apron is the blue section on above diagram. 


Content last reviewed 08.16.2022