Re-Mark of Runway 17-35

Re-Mark of Runway 17-35


Project Manager

Paul Priegel, Airport Director


What We're Doing

This project is required maintenance and upkeep to re-paint airfield markings on our primary Runway 17-35. 


Anticipated Milestones

  • Anticipated Date (Design): February 2018

  • Anticipated Date (Construction): July 2018

  • Anticipated Date (Completion): July 2018


Benefits of the Project

This is required approximately every three years to ensure the runway markings are visible to allow pilots to safely navigate the primary runway.     


Budget & Funding

This project will be funded with 90% FAA AIP Grant funds and 10% with local funds. 


Project Management

Project Management Graph


Updates

  • July 2018: Project begins

  • August 2018: Due to weather conditions, completion postponed until Spring 2019

  • May 2019: Project Completed


Actions by City Council


Image(s)

Image of runway