Paul Priegel, Airport Director
Anticipated Date (Design): February 2018
Anticipated Date (Construction): July 2018
Anticipated Date (Completion): July 2018
This is required approximately every three years to ensure the runway markings are visible to allow pilots to safely navigate the primary runway.
This project will be funded with 90% FAA AIP Grant funds and 10% with local funds.
Year Funded: FY2018 and FY2019
Funding Source: 90% Federal Grant / 10% City of Stillwater
Project Budget: Estimated at $112,941
Expenditure to date: $112,941
July 2018: Project begins
August 2018: Due to weather conditions, completion postponed until Spring 2019
May 2019: Project Completed