Project Manager: David Barth, P.E. | City Engineering
SUA Project No. 15WC03, Water 2040
Visit the GIS Infrastructure Map to see where city infrastructure projects are happening.
This project includes construction of a new water distribution booster pump station (19th BPS) on the north west corner of 19th Avenue & Range Road, and 2.5 miles of 12-inch water transmission line to connect the pump station to 44th Water Tower.
The new 19th BPS, water transmission line and 44th Water Tower will establish a new municipal and rural water distribution zone for the area (see map below). This new zone eliminates small temporary pump stations currently used to maintain City Standard water pressure of 40psi at Boulder Creek, Hidden Oaks, and Kenslow Farms developments. The new system also assimilates the existing Southwest Zone developments of Nottingham, Woodlake I and Woodlake II. This new zone will help to relieve the overburdened Southwest Distribution Zone during high demand periods, as well as, lifts the Twin Towers Moratorium for future development growth.
June 15, 2017: Pre-bid meeting was held June 1, 2017. Bids are due Wednesday, June 21, 2017.
July 24, 2017: Bids were opened on June 28th and the project will be awarded on August 7th.
August 10, 2017: Wynn Construction Co., Inc. was awarded the construction contract.
September 11, 2017: Notice to Proceed was issued.
September 2017: Post card construction notice sent in September to residences within the area that will be impacted by work.
October 13, 2017: Pump station foundation earthwork is underway.
November 17, 2017: Concrete foundation progresses on BPS.
December 20, 2017: Building foundation complete
January 15, 2018: Water installation progresses along south Range Road in new easement adjacent to ROW.
February 7, 2018: Water line installation progresses to 44th Tower.
February 27, 2018: Pump Station slab is complete. Contractors continue to work on site utilities and the water line down Range Road.
March 13, 2018: Pump Station building CMU wall complete.
April 23, 2018: Pump Station building is nearly complete. Contractors continue to work on site utilities and the water line down Range Road.
October 11, 2018: The water line work is nearly complete. The booster pump station is scheduled to be completed end of 2018.
March 29, 2019: All water line tie-ins are complete and demolition of the Twin Towers is in progress.
10.19.15 | SUA-15-52 | Real Estate Authorization
6.5.17 | CC-17-85 | Acceptance of Easements
![]() |
(405) 372-0025 |
![]() |
723 S. Lewis St. Stillwater, OK 74074 |
|
New City Hall Hours: Mon-Thu: 7:30 am-5:30 pm Friday: 7:30-11:30 am |