Airport Industrial Access Road Water Line Relocation

Airport Industrial Access Road Water Line Relocation

Project Manager

Water Utilities Engineering / Shannon Wilder

SUA Project No. 21WL02

Visit the GIS Infrastructure Map to see where city infrastructure projects are happening.


What We're Doing

The City of Stillwater and Stillwater Utilities Authority are relocating a portion of water line along the Airport Industrial Access Road. 


Anticipated Milestones

  • Anticipated Date (Design): Winter 2021
  • Anticipated Date (Construction): Spring 2021
  • Anticipated Date (Completion): Fall 2021

Benefits of the Project

This section of water line needs to be relocated due to conflicts with the proposed road reconstruction design.


Budget & Funding

  • Year Funded: FY21
  • Funding Source: Water Capital Fund
  • Project Budget: $39,000 for design
  • Expenditures to date: $0

Project Management


Updates

Sept. 14, 2020: SUA approved the Professional Services Agreement with Olsson Associates to provide design and construction services.

Nov. 20, 2020: 50% design plans were received from Engineer.

Dec. 07, 2020: Staff provided comments to Engineer on design plans. 

Jan. 04, 2021: Olsson has provided 90% design plans for staff review.

Feb. 18, 2021: Olsson is progressing with final plans and permitting. 


Actions Authorized by Stillwater Utilities Authority (SUA)

  • 09.14.20  | SUA-20-32 |  PSA with Olsson Associates

Image

Map showing the proposed new location of the water line