College Gardens

College Gardens and Additional Areas for Water Line Replacement

Project Manager

Water Utilities Engineering / Shannon Wilder

SUA Project No. 21WL04

Visit the GIS Infrastructure Map to see where city infrastructure projects are happening.


What We're Doing

The City of Stillwater and the Stillwater Utilities Authority are replacing water lines in the College Gardens Area (University to Admiral, Western to Redwood), Westwood/University Area (Willis to Jefferson, University to 6th Avenue), and in the Wicklow Area (8th Avenue and 10th Avenue, and Devon to Western). 


Anticipated Milestones

  • Anticipated Date (Design): Late 2021
  • Anticipated Date (Construction): Early 2022
  • Anticipated Date (Completion): Early 2024

Benefits of the Project

The waterlines in this area are deteriorated and in need of replacement.


Budget & Funding


Project Management


Updates

Sept. 14, 2020: Kimley-Horn & Associates was selected, and approved by SUA, to provide design services. 

Oct. 21, 2020: The kick-off meeting between staff and the Engineer occurred October 5th. Staff is currently gathering necessary data from the project areas to send to the Engineer.


Actions Authorized by Stillwater Utilities Authority (SUA)

  • 09.14.20  | SUA-20-31 |  Professional Services Agreement

Image

Map showing areas of water line replacement